DONICA ROAD WEEKLY UPDATE - MARCH 30, 2026

Phase 1 Donica Road Sewer Extension Project construction begins the week of March 30 with four major areas of work completed this spring by our construction partner Albanese D&S Inc. and their contractors:

March 30 – May 29

  • Directional borings for the gravity main, force main and Anthony’s service lateral under Route 1
  • Laying the gravity sewer and force main along the westernmost southbound lane on Route 1
  • Drilling for blasting associated with the sewer trench on Donica Road. Anticipated times for blasting are during the week of April 12, updates will be provided. Drilling requires a 1-lane traffic pattern on weekdays 7:00 AM – 5:00 PM. Access from both ends of Donica Road will be available and will keep traffic impacts to minimum
  • Installing the sewer main and service laterals to the property line; additional updates will be provided in early May

As with any project, there may be adjustments to timing

Each week, we will keep you updated with accomplishments and the upcoming construction milestones via email—thanks for signing up! Updates will also be available online at yorksewerdistrict.org and on Facebook, Instagram and X.

COMING SOON!

Information from the District on septic system testing and planning for hook-ups this fall

Know a neighbor who needs this info, too?

Forward this email! Or let them know that they can sign up for these weekly updates online at yorksewerdistrict.org or by emailing York Sewer District at media@yorksewerdistrict.org from their preferred email account.

Working smart, working safe.

York Sewer District is proud to partner with Albanese on the Donica Road Sewer Extension. They specialize in large-scale complex heavy civil construction that involves utilities, deep excavation and road construction.

Albanese brings a skilled professional workforce to our partnership that includes laborers, heavy equipment operators, truck drivers, and mechanics.

The Donica Road crews are efficiently scheduled to work on both Donica Road and York Water District’s spring project at the Nubble. The crew will alternate between the two project sites based on the blasting schedule.

LEARN MORE

It’s been such a cold, snowy winter! We’re ready for spring and looking forward to getting your new sewer hook-ups constructed this summer.

York Sewer District is committed to clear communications and project transparency. 

For questions about the Donica Road project, process, construction phases or to learn more about how to connect your property to the new sewer extension, visit us online at yorksewerdistrict.org or email our team today media@yorksewerdistrict.org.