Construction Schedule Spring ‘26
The Donica Road Project has three major phases of construction. We'll provide monthly updates throughout the 9-month project and as major milestones are completed.
March Milestones
- March 16–20: Pre-construction photos
- March 23–27: Pre-blast survey (notification will go out to property owners impacted in advance)
- March 30–April 3: Begin project mobilization and construction